Takt Time Calculator

Determine the pace of production needed to meet customer demand.

Takt Time Calculator

Takt unit:
Takt Time
1.05 m
per unit — simple mode
Net Available Time
420 min
25200 sec
Units per Hour
57.14
Takt per Operator
5.25 m

Formulas

ModeNet Available TimeTakt Time
Simple(Shift × 60) − BreaksNet Available / Demand
Batch(Shift × 60) − BreaksNet Available / (Demand × Batch)
WeeklyNet Available × Days/WeekWeekly Time / Demand
Status:FASTERcycle shorter than takt,SLOWERcycle longer than takt,ON-TAKTexact match

Takt comes from the German word for "metronome." Use it to keep production synchronized with customer demand.

Infinio Tools